Sir,

     This is for your Information the site status till today the 22nd Feb.

 

1)      Chatri No 1 Flashing No F1 and F2 Fixed.

2)      Cladding of sheets Production completed of chatri no 1.

3)      Cladding of three Rows completed P1,P2,and P3.

4)      Cladding Sheets of Chatri No 2 P1,P2,P3 and P4 production completed.

5)      On The 23rd Feb Flashing for Chatri No2 i.e F1 and F2 will be completed and Installation,

Work will start.

Waterproofing work is happening on the Domes As it gets completed we will start Production

And Installation of the Domes.

 

Regards.

N.Tandon.