Dear Mr. Vijaykumar.

We would like to inform you that we will start installing the hazardous waste shed, car parking shed and the balance roof area in one of the main bay where 70% of roof has already been installed.

Please note we wiil mobalise our team by Friday (1-7-11) .It will take us maximum 10 to 12 days starting from (1-7-11) to finish the above mentioned sheds provided there is no rain during the time of installation.

 

Regards

Kalandar.M

 

From: VIJAYKUMAR [mailto:cdvijaykumar@yahoo.com]
Sent: Monday, June 27, 2011 8:37 PM
To: sales
Cc: kishor@mehtalia.com; sparthe@its.jnj.com; sbhat@its.jnj.com
Subject: Non submission of sheeting programme

 

27.06.2011

Mumbai

 

Dear Mr.M.Kalandar

 

As discussed and committed by you in the todays meeting the balance work completion programme should be sent to us for progress monitoring purpose which you have failed to comply

 

Kindly comply the requirement
 

VIJAYKUMAR
Mobile:+919930916404 

 

 


From: sales <sales@vijaynath.in>
To: cdvijaykumar@yahoo.com
Cc: kishor@mehtalia.com; SBHAT@its.jnj.com; sparthe@its.jnj.com; sales@vijaynath.com; admin@vijaynath.in
Sent: Mon, 27 June, 2011 1:53:14 PM
Subject: Johnson & Johnson Roofing.

MOM . Johnson & Johnson site Mulund .

 

Kalandar.M  (Vijaynath Interiors & Exteriors pvt Ltd)

Santosh Tanpur (Vijanath Interiors & Exteriors pvt Ltd)

Santosh Parthe. ( Johnson & johnson)

Vijaykumar  ( B Mehtalia).

 

As discussed in the meeting we would like to highlight following points.

1)      Vijaynath to mobalise the roofing team by Friday (1-7-11)

2)      Vijaynath will first start installing the parking shed and hazardous waste shed.

3)      Vijaynath will remove the main shed and start installing the sheets only after discussin it with Johnson team.

4)      Vijaynath will submit soft copies for all the roofing drawings to Mr. Vijayjumar from b. Mehtalia.

5)      Mr. Vijaykumar to discuss any site related issues with Mr.Kalandar.

Regards

Kalandar.m